Performance Status Calculations

This topic provides additional information about the formulas used to calculate the performance status metrics shown on the Portfolio Performance Status page. The Portfolio Performance Status page displays summarized schedule and cost or labor unit data based on one of three performance metrics you select:

For each metric, to date and forecast data are provided at the group, project, and WBS levels. The values you specify in the Performance Threshold area of the My Preferences page Global tab determine which visual indicators apply to each metric.

Schedule

When you select Schedule, the page displays the following calculated data:

Schedule to Date

(Baseline Duration multiplied by Performance % Complete) minus (Baseline Duration multiplied by Schedule % Complete)

Performance % Complete = Earned Value divided by BAC

Schedule % Complete = Planned Value divided by BAC

Labor Units to Date

Earned Value Labor Units minus Actual Labor Units

threshold percentage calculation = Labor Units to date divided by Earned Value Labor Units

Cost to Date

Earned Value — Actual Cost

threshold percentage calculation = Cost to date/Earned Value

Schedule at Completion

Remaining Finish Date - Baseline Finish Date

Labor Units at Completion

BAC Labor Units - EAC Labor Units

threshold percentage calculation = Labor Units at Completion/BAC Labor Units

Cost at Completion

BAC- EAC

threshold percentage calculation = Cost at Completion/BAC

Earned Value

When you select Earned Value, the page displays the following calculated data:

Schedule to Date (SV)

Earned Value Labor Units - Planned Value Labor Units

threshold percentage calculation = Schedule to Date/Planned Value Labor Units

Labor Units to Date (CV)

Earned Value Labor Units - Actual Labor Units

threshold percentage calculation = Labor Units to Date/Earned Value Labor Units

Cost to Date (CV)

Earned Value - Actual Cost

threshold percentage calculation = Cost to Date/Earned Value

Schedule at Completion

BAC*SVI

SVI = SV/Planned Value Labor Units

threshold percentage calculation = Schedule at Completion/BAC

Labor Units at Completion

BAC Labor Units*CVI

threshold percentage calculation = Labor Units at Completion/BAC Labor Units

Cost at Completion

BAC*CVI

threshold percentage calculation = Cost at Completion/BAC

Index

When you select Index, the page displays the following calculated data:

SPI

SPI = bcwp / bcws

CPI

CPI = bcwp / ACWP

ACWP = act_equip_cost + act_expense_cost + act_work_cost

TCPI

TCPI = (BAC – bcwp) / (EAC – ACWP)

BAC = base_equip_cost + base_expense_cost + base_work_cost

EAC = (act_equip_cost + act_expense_cost + act_work_cost) + (remain_equip_cost + remain_expense_cost + remain_work_cost)

ACWP = act_equip_cost + act_expense_cost + act_work_cost