Recalculating Assignment Costs

Recalculate assignment costs to update price per time values on activities. This ensures that project costs reflect any updates.

To recalculate assignment costs:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. On the Activities page:
    1. Select an activity.
    2. Click Actions and select Recalculate Assignment Costs.
    3. In the Recalculate Assignment Costs dialog box:
    4. (Optional) Select the Synchronize overtime factor while recalculating costs option to synchronize the overtime factor defined for each resource when recalculating costs.
    5. Click Recalculate.

Tips