Configuring General Project Preferences

Configure general project preferences to specify general information concerning the project such as when the fiscal year begins.

To configure general project preferences:

  1. Click Projects.
  2. On the Projects navigation bar, click EPS.
  3. On the EPS page:
    1. Select a project or EPS node.

      Note: If an EPS node is selected, the data shown represents the default settings for the fields. These defaults and the selections you make in any fields will be applied to all projects which match the applied filter in the selected EPS node and all child nodes.

    2. Click Row Actions and select Set Project Preferences.
    3. In the Project Preferences dialog box, click General.
    4. On the General page configure the WBS Code Separator field and select a month for the Fiscal year begins on the first day of list.
    5. Click OK.

Related Topics

Configuring Project Preferences

Configuring History Settings for Analytics

Configuring Project Calculations

Configuring Project Defaults

Configuring Project Summarization and Publication Services

Configuring P6 Team Member Status Update Reviews

Configuring P6 Team Member View Preferences



Legal Notices | Your Privacy Rights
Copyright © 1999, 2020

Last Published Friday, October 1, 2021