Configure the standard work week for the calendar to set the work and nonwork days and hours.
To configure the standard work week:
- Click the User menu and select My Calendar.
- On the My Calendar page, click the Standard Work Week tab.
- On the Standard Work Week tab, enter a number of hours for each work day in the total hours field.
- Configure the work periods in the chart:
- Create a new work period by clicking and dragging on the chart.
- Create multiple work periods for each day.
- Drag a work period on the chart to have it start earlier or later in the day.
- Make a work period longer or shorter by clicking and dragging the lower edge of the work period on the chart.
- Delete a work period by selecting the work period in the chart and selecting .
- Click Save.