Units Columns of the Activity Table

Actual Labor Units field

The number of units expended for all labor resources assigned to the activity.

Actual Nonlabor Units field

The number of nonlabor units that have been expended on the activity.

Actual This Period Labor Units field

The number of labor units used during this financial period.

If period performance is stored, the calculation is Actual Labor Units minus the sum of the stored Actual This Period Labor Units fields for all previous periods.

If the period performance is not stored, Actual This Period Labor Units is the same as Actual Labor Units.

Actual This Period Nonlabor Units field

The nonlabor units used during this financial period.

If period performance is stored, the calculation is Actual Nonlabor Units minus the sum of the stored Actual This Period Nonlabor Units fields for all previous periods.

If the period performance is not stored, Actual This Period Nonlabor Units is the same as Actual Nonlabor Units.

At Completion Labor Units field

The sum of the actual plus remaining units for all labor resources assigned to the activity.

It is the same as the planned labor units if the activity is not started, and the actual labor units once the activity is completed.

Calculated as Actual Labor Units plus Remaining Labor Units.

At Completion Nonlabor Units field

The non labor units at completion. The sum of the actual plus remaining units for all nonlabor resources assigned to the activity.

It is the same as the planned nonlabor units if the activity is not started, and the actual nonlabor units once the activity is completed.

Calculated as Actual Nonlabor Units plus Remaining Nonlabor Units.

BL Project Actual Labor Units field

The actual units for all labor resources assigned to the activity in the project baseline.

BL Project Actual Nonlabor Units field

The actual units for all actual nonlabor resources assigned to the activity in the project baseline.

BL Project Labor Units field

The units for all labor resources assigned to the activity in the project baseline.

BL Project Nonlabor Units field

The units for all nonlabor resources assigned to the activity in the project baseline.

BL1 Actual Labor Units field

The actual units for all labor resources assigned to the activity in the primary baseline.

BL1 Actual Nonlabor Units field

The actual units for all nonlabor resources assigned to the activity in the primary baseline.

BL1 Labor Units field

The units for all labor resources assigned to the activity in the primary baseline.

Calculated as Baseline Actual Labor Units plus Baseline Remaining Labor Units.

BL1 Nonlabor Units field

The units for all nonlabor resources assigned to the activity in the primary baseline.

Planned Labor Units field

The planned number of units for all labor resources assigned to the activity.

Planned Nonlabor Units field

The planned units for all nonlabor resources assigned to the activities in the project.

Remaining Labor Units field

The remaining units for all labor resources assigned to the activity.

The Remaining Labor Units reflect the work remaining to be done for the activity. Before the activity is started, the remaining units are the same as the planned units. After the activity is completed, the remaining units are zero.

Remaining Nonlabor Units field

The remaining units for all nonlabor resources assigned to the activities.

The remaining units reflect the work remaining to be done for the activity. Before the activity is started, the remaining units are the same as the planned units. After the activity is completed, there are zero remaining units.

Variance BL Project - Labor Units field

The difference between baseline labor units and at completion labor units. Baseline variance columns only use data from visible activities. If you need to see variance for the whole project, remove any filters applied to the view.

Calculated as BL Project Labor Units minus At Completion Labor Units.

Variance BL Project - Nonlabor Units field

The difference between the baseline nonlabor units and the at completion nonlabor units. Baseline variance columns only use data from visible activities. If you need to see variance for the whole project, remove any filters applied to the view.

Calculated as BL Project Nonlabor Units minus At Completion Nonlabor Units.

Variance BL1 - Labor Units field

The difference between primary baseline labor units and the at completion labor units. Baseline variance columns only use data from visible activities. If you need to see variance for the whole project, remove any filters applied to the view.

Calculated as BL1 Labor Units minus At Completion Labor Units.

Variance BL1 - Nonlabor Units field

The difference between the primary baseline nonlabor units and the at completion nonlabor units. Baseline variance columns only use data from visible activities. If you need to see variance for the whole project, remove any filters applied to the view.

Calculated as BL1 Nonlabor Units minus At Completion Nonlabor Units.