Durations Columns of the Activity Table

Actual Duration field

The total working time from the activity Actual Start date to the Actual Finish date for completed activities, or the total working time from the Actual Start date to the data date for in-progress activities.

The actual working time is computed using the activity's calendar.

At Completion Duration field

The total working time from the activity's current start date to the current finish date.

The current start date is the planned start date until the activity is started, and then it is the actual start date. The current finish date is the activity planned finish date while the activity is not started, the remaining finish date while the activity is in progress, and the actual finish date once the activity is completed. The total working time is calculated using the activity's calendar.

BL Project Actual Duration field

The actual duration of the activity in the project baseline. The duration is the total working time from the activity actual start date to the actual finish date.

The total working time is calculated using the activity's calendar.

BL Project Duration field

The duration of the activity in the project baseline. The duration is the total working time from the activity current start date to the current finish date.

Calculated as Actual Duration plus Remaining Duration.

The total working time is calculated using the activity's calendar.

BL Project Free Float field

The free float of the activity in the project baseline.

BL Project Remaining Duration field

The remaining duration of the activity in the project baseline.

BL Project Total Float field

The total float of the activity in the project baseline.

BL1 Actual Duration field

The actual duration of the activity in the primary baseline. The duration is the total working time from the activity actual start date to the actual finish date.

The total working time is calculated using the activity's calendar.

BL1 Duration field

The duration of the activity in the primary baseline. The duration is the total working time from the activity current start date to the current finish date.

Calculated as Actual Duration plus Remaining Duration.

The total working time is calculated using the activity's calendar.

BL1 Free Float field

The free float of the activity in the primary baseline.

BL1 Remaining Duration field

The remaining duration of the activity in the primary baseline.

BL1 Total Float field

The total float of the activity in the primary baseline.

Free Float field

The amount of time the activity can be delayed before delaying the start date of any successor activity.

Maximum Duration field

The longest duration for the activity. Required for three point estimation if quantitative risk analysis will be performed in Oracle Primavera Cloud.

Minimum Duration field

The shortest duration for the activity. Required for three point estimation if quantitative risk analysis will be performed in Oracle Primavera Cloud.

Most Likely Duration field

The most likely duration for the activity. Required for three point estimation if quantitative risk analysis will be performed in Oracle Primavera Cloud.

Planned Duration field

The expected amount of time required to complete an activity.

The planned working time is calculated using the activity's calendar. The duration is measured from the activity's planned start date to its planned finish date.

Remaining Duration field

The total working time from the activity remaining start date to the remaining finish date.

The remaining working time is calculated using the activity's calendar. Before the activity is started, the remaining duration is the same as the planned duration. After the activity is completed the remaining duration is zero.

Remaining Float field

The amount of time remaining by which the activity can be delayed before delaying the project finish date.

Calculated as Late Finish minus Remaining Finish. If the remaining finish is the same as the early finish (in general, when the activity is not started), then the remaining float is the same as the total float.

Total Float field

The amount of time the activity can be delayed before risking a delay to the project finish date.

A float of zero hours indicates that the activity cannot be delayed at all and a negative float indicates that the project is already behind schedule. In a complex schedule, negative total float on some activities might not cause a delay to the project finish date.

Calculated as Late Start minus Early Start or as Late Finish minus Early Finish.

Variance BL Project - Duration field

The duration between the activity's baseline duration and the at completion duration. Baseline variance columns only use data from visible activities. If you need to see variance for the whole project, remove any filters applied to the view.

Calculated as Planned Duration minus At Completion Duration.

Variance BL Project - Finish Date field

The duration between the current project finish date in the baseline project finish date. Baseline variance columns only use data from visible activities. If you need to see variance for the whole project, remove any filters applied to the view.

Calculated as Finish minus BL Project Finish.

Variance BL Project - Start Date field

The duration between the current project start date and the baseline start date. Baseline variance columns only use data from visible activities. If you need to see variance for the whole project, remove any filters applied to the view.

Calculated as Start minus BL Project Start.

Variance BL1 - Duration field

The duration between the activity's primary baseline duration and the at completion duration. Baseline variance columns only use data from visible activities. If you need to see variance for the whole project, remove any filters applied to the view.

Calculated as BL1 Duration minus At Completion Duration.

Variance BL1 - Finish Date field

The duration between the current project finish date and the primary baseline finish date. Baseline variance columns only use data from visible activities. If you need to see variance for the whole project, remove any filters applied to the view.

Calculated as Finish minus BL1 Finish.

Variance BL1 - Start Date field

The duration between the current project start date and the primary baseline start date. Baseline variance columns only use data from visible activities. If you need to see variance for the whole project, remove any filters applied to the view.

Calculated as Start minus BL1 Start.