Summary Columns of the EPS Table

Contains Summary Data option

Determines whether the project has been summarized. If the checkbox is marked, the project has been summarized.

Enable Summarization option

Determines whether a project will be summarized. If you select this option, the fields on the Summarization page are enabled. If this option is cleared, the project will not be summarized.

Last Summarized Date field

The date the project was last summarized. This is useful for assessing whether summary data for the project is current.

This field is blank for projects that have not been summarized.

Summarize Resources/Roles by WBS option

Determines whether resource and role summaries should be created at WBS level for the project. If this option is selected, then P6 will create summary data for resources and roles to the level determined by Summarize to WBS level.

Summarize to WBS Level list

Determines the number of summary WBS levels stored in the database.