Dates Columns of the EPS Table

Actual Finish field

The date on which the project is complete.

This field is empty until all activities in the project have an actual finish date.

Actual Start field

If the work has started, the date work on the project began. For an EPS, the actual start is the earliest actual start among all projects within it.

Anticipated Finish field

The expected finish date of the project, EPS node, or WBS level used during the planning phase. This date is manually entered and is not affected by scheduling.

If there are no children elements, the anticipated finish is the finish date listed for the item in the table.

The Anticipated Finish date is used as the Finish date if there are no activities assigned to the project or WBS.

Anticipated Start field

The expected start date of the project, EPS node, or WBS level used during the planning phase. This date is manually entered and is not affected by scheduling.

If there are no children elements, the anticipated start is the start date listed for the item in the table.

The Anticipated Start date is used as the Start date if there are no activities assigned to the project or WBS.

BL Finish field

The current latest finish date of all activities in the project baseline.

BL Start field

The current earliest start date of all activities in the project baseline.

Data Date field

The progress point, or "as-of date", for activities in the project. Project status is up-to-date as of the data date. You can set the data date when you schedule the project or apply actuals, or you can set it manually. Set it manually if resources manually update activity progress and you do not plan to reschedule the project or apply actuals.

Finish field

The current finish date of the project. For not started and in-progress projects, this is the latest early finish date from all activities in the project. For completed projects, this is the latest actual finish date derived from all activities. For projects with no activities, the Finish Date is equal to the Anticipated Finish date if one is defined. For projects with no activities and no Anticipated Finish date, the Finish Date field is blank.

Forecast Finish Date field

The end date optionally used by the project scheduler. This date can only be set in P6 Professional.

Forecast Start Date field

The start date optionally used by the project scheduler.

This date can only be set in P6 Professional.

Last Apply Actuals Date field

The last date actuals were applied to this project.

Last Leveled Date field

The most recent date when the project was leveled.

Last Scheduled Date field

The most recent date when the project was scheduled.

Must Finish By field

The optional date constraint you can specify for the project end date.

Planned Finish Date field

The latest planned finish date of all projects or templates within the EPS.

Planned Start Date field

The date the project is scheduled to start.

Post-Response Pessimistic Finish Date field

The Post-Response Pessimistic Finish Date calculated in Oracle Primavera Cloud during quantitative risk analysis.

Post-Response Pessimistic Start Date field

The Post-Response Pessimistic Start Date calculated in Oracle Primavera Cloud during quantitative risk analysis.

Pre-Response Pessimistic Finish Date field

The Pre-Response Pessimistic Finish Date calculated in Oracle Primavera Cloud during quantitative risk analysis.

Pre-Response Pessimistic Start Date field

The Pre-Response Pessimistic Start Date calculated in Oracle Primavera Cloud during quantitative risk analysis.

Project Forecast Start field

The planned start date of the project based on a what-if scenario designed to simulate project performance and outcomes.

Project Planned Start field

The expected start date for the project.

Scheduled Finish field

The calculated latest early finish date, which is based on the schedule most recently generated for the project.

Start field

The current start date of the project. For a not started project, this is the project's planned start date. For a project that has started or is complete, this is the project's actual start date. For projects with no activities, the start date is equal to the anticipated start date if one is defined; if no anticipated start is defined, then the start date is equal to the project's planned start date.



Legal Notices | Your Privacy Rights
Copyright © 1999, 2020

Last Published Friday, October 1, 2021