Units Columns of the Assignments Table

Actual Overtime Units field

The actual overtime units worked by the resource on the activity.

This value is calculated from timesheets when project actuals are applied or can be entered directly by the project manager.

Actual Regular Units field

The actual non-overtime units worked by the resource on the activity.

This value is calculated from timesheets when project actuals are applied or can be entered directly by the project manager.

Actual This Period Units field

The labor, nonlabor, and material units used during this financial period.

If period performance is stored, the calculation is Actual Units minus the sum of the stored Actual This Period Units fields for all previous periods.

If the period performance is not stored, Actual This Period Units is the same as Actual Units.

Actual Units field

The sum of the actual non-overtime and the overtime units worked by the resource on the activity.

Calculated as Actual Regular Units plus Actual Overtime Units.

Values for Actual Regular Units and Actual Overtime Units are obtained from either timesheets when project actuals are applied, or directly from the updated fields in the interface.

At Completion Units field

The sum of the actual units and remaining units for the resource assignment on the activity.

Calculated as Actual Units plus Remaining Units.

Pend Remaining Units field

The estimate of the resource's remaining units on this activity.

The Pend Remaining Units value is entered by each resource using timesheets. This value is copied to the resource's remaining units for the activity when project actuals are applied. The project manager specifies whether resources update their percent complete or remaining units for each project.

Planned Units field

The planned units of work for the resource assignment on the activity.

Remaining Units field

The remaining units of work to be performed by the resource on the activity.

Calculated as Planned Units minus Actual Units.

Staffed Remaining Units field

The remaining units for resource assignments that have filled a role.

Unstaffed Remaining Units field

The remaining units for resource assignments that have not filled a role.