Risk Exposure (Pre-response)

Risk Exposure category

Exposure field

The monetary impact value for each risk calculated from the values selected for the probability and cost impact.

Exposure provides data that is generally used during the analysis and prioritization phases of the risk management process. The difference in exposure for a risk and its associated response plan is indicative of the effectiveness of the response plan.

Calculated as Probability midpoint times Cost midpoint. A midpoint is calculated by adding the lowest and the highest values for the threshold and dividing the sum by two.

Exposure Finish field

The latest finish date of all activities associated with the risk.

If no activities are associated with the risk, the exposure finish date is set to the project Finish date. If the project Finish date is not set, the project Scheduled Finish date is used. If the project Scheduled Finish date is not set, the project Must Finish By date is used. If this date is not set, Exposure Finish is set to the project start date.

Exposure Start field

The earliest start date of all activities associated with the risk.

If no activities are associated with the risk, the Exposure Start date is the project Start date.

Related Topics

Risk Exposure Calculations