P6 Team Member Interfaces Field Names

P6

P6 Team Member Interfaces

Available to...

Remaining Start

Start By

All

Actual Start

Started

All

Remaining Finish

Finish By

All

Actual Finish

Finished

All

Remaining Duration

Remaining Duration

All

Activity % Complete

% Complete

Activity owner and user assigned Team Member work distribution filter

Actual Units

Time Spent

Resource assignment

Actual Labor Units

Time Spent (Labor)

Activity owner and user assigned Team Member work distribution filter

Actual Nonlabor Units

Time Spent (Nonlabor)

Activity owner and user assigned Team Member work distribution filter

Remaining Units

Time Left

Resource assignment

Remaining Labor Units

Time Left (Labor)

Activity owner and user assigned Team Member work distribution filter

Remaining Nonlabor Units

Time Left (Nonlabor)

Activity owner and user assigned Team Member work distribution filter

Expected Finish

Expected Finish

Activity owner and user assigned Team Member work distribution filter