My Risks Portlet of the Dashboards Page

Overview

Using your portfolio, project, or project code filter criteria specified for the current dashboard, the My Risks portlet displays information about your associated risks. You can customize the portlet to specify the columns of information you want to display, as well as the types of risks you want to appear.

Screen Elements

Customize link

See Customize Risks Dialog Box.

Name field

The name of the risk.

General category

ID field

The unique identifier for the risk.

Name field

The name for a particular type of risk classification.

Owner field

The resource who has ownership of the risk.

Identified By field

The name of the resource who identified the risk.

Type list

Determines whether a risk is a threat or an opportunity.

A threat will have a negative impact on your project, while an opportunity can have a perceived benefit to the project.

Status field

The current state of the risk.

Proposed: The risk is identified and awaits approval.

Open: The risk is approved as a valid risk to the project.

Active: The risk is currently impacting the project.

Rejected (Closed): The risk is not seen as a valid risk to the project and therefore will not be tracked and managed by the project. The data for this risk cannot be modified once it is closed.

Managed (Closed): The risk occurred and was successfully managed by the project team and is no longer an active risk. The data for this risk cannot be modified once it is closed.

Impacted (Closed): The risk occurred, impacted the project and is no longer an active risk. The data for this risk cannot be modified once it is closed.

Description field

The description of the risk.

Cause field

The description of the cause of the risk.

Effect field

The resulting effect of the presence of the risk.

Notes field

The notes or comments captured for the associated risk.

User Defined category

User Defined fields

The fields defined by your P6 administrator that are not standard in the application but are necessary to capture additional data.

Tips

The "No information is available" message appears when your project and risk filtering criteria excludes risks that are associated with you, or there are no risks associated with you.

Getting Here

  1. Click Dashboards.
  2. On the Dashboards page, select a dashboard.
  3. On the dashboard, expand the My Risks portlet.

Related Topics

About Risks

Working with Project Risks



Legal Notices | Your Privacy Rights
Copyright © 1999, 2020

Last Published Friday, October 1, 2021