Email Statusing Service Activity Filter Options

As a team member or project manager, you must follow the syntax and formatting for the filter options below when sending a request to Email Statusing Service.

Filter Options

There are three types of request filters: Status, Time Frame, and Project. A status request is a minimum requirement; a time frame and project request are optional extensions to the status request.

For team members, a valid request for an activity list would appear in the email subject line as:

<Status> <Time Frame, optional> <Project, optional>

Note: If you need assistance with the options, syntax, or required formatting of these messages, send an email message with only the word Help or a ? in the subject line to receive more detailed instructions. In addition, if your status request message is ever invalid, you will be notified by email.

For project managers, a valid request to send a notification email to team members would appear in the subject line as:

Notify <Status> <Time Frame, optional> <Project, optional>

Status Options

Active

Activities that are in progress or have not started.

Due

Activities scheduled to finish today.

Overdue

Activities that were scheduled to finish prior to today.

Completed

Activities where the finished date is today's date.

Starting

Activities that are scheduled to start today.

Starred

Activities team members marked as important. This filter can only be combined with a Project ID or Project Name filter. The starring feature is not available to users assigned Team Member work distribution filters.

Time Frame Options

Requests by status can optionally be filtered based on a specified number of days, weeks, or months, or by specifying today, tomorrow, or yesterday.

Active in next <number> <units of time>

Activities that are in progress or scheduled to start in the next number of days, weeks, or months.

Example: Active in next 3 weeks

Active Today

Activities that are in progress or are scheduled to start on or before today's date.

Active Tomorrow

Activities that are in progress or are scheduled to start on or before tomorrow's date.

Due in next <number> <units of time>

Activities that should be completed in the next number of days, weeks, or months.

Example: Due in next 5 days

Due Today

Activities scheduled to finish today.

Due Tomorrow

Activities that are scheduled to finish tomorrow.

Completed in last <number> <units of time>

Activities that were completed in the last number of days, weeks, or months.

Example: Completed in last 3 days

Notes:

Completed Today

Activities where the finished date is today's date.

Completed Yesterday

Activities where the finished date is yesterday's date.

Starting in next <number> <units of time>

Activities that are scheduled to start in the next number of days, weeks, month.

Example: Starting in next 1 month

Starting Today

Activities that are scheduled to start today.

Starting Tomorrow

Activities that are scheduled to start tomorrow.

Project Options

Requests by status can optionally be filtered based on an active project name or project ID.

on Project <Project ID or Name>

Restricts the results of the requested status and optional time frame filter to the activities that belong to the specified active project. If no project is specified, all active projects for which you have access rights will be included.

Examples:

Fields Available for Activity Status Updates

The fields available in the email are assigned by the project manager in P6. Also, in P6, team members are assigned as either a resource assignment, an activity owner, or a user with a Team Member work distribution filter. Project managers should let team members know what fields are assigned to them and whether they are a resource assignment, an activity owner, or a user with a Team Member work distribution filter because some of the status fields depend on their role.

The updates you can make to the fields that are returned depend on the activity status (Not Started, In Progress, or Completed). Use the following table to determine which fields can be updated for a Not Started, In Progress, or Completed activity.

Table of Activity Status Fields Available by Email

Resource Assignment

Field

Status: Not Started

Status: In Progress

Status: Completed

Sample Value

Start/Started Date

Yes

Yes

Yes

15-APR-2012

Finish/Finished Date

Yes

Yes

Yes

18-APR-2012

Time Spent

Yes

Yes

Yes

1d 2h

Time Left

Yes

Yes

No

2d 6h

Remaining Duration

Yes

Yes

No

5d

Finished (Y/N)

Yes

Yes

No

N

Starred (Y/N)

Yes

Yes

No

N

Activity Owner or User Assigned a Team Member Work Distribution Filter

Field

Status: Not Started

Status: In Progress

Status: Completed

Sample Value

Start/Started Date

Yes

Yes

Yes

15-APR-2012

Finish/Finished Date

No

No

Yes

18-APR-2012

Activity % Complete (see notes)

Yes

Yes

No

25%

Expected Finish

Yes

Yes

No

30-APR-2012

Time Spent (Labor/Nonlabor)

Yes

Yes

Yes

1d 2h

Time Left (Labor/Nonlabor)

Yes

Yes

No

2d 6h

Remaining Duration

Yes

Yes

No

4d

Finished (Y/N)

Yes

Yes

No

N

Starred (Y/N) (see notes)

Yes

Yes

No

N

Notes for Activity % Complete:

Note for Starred (Y/N): The starring feature is not available to users assigned Team Member work distribution filters.