Linking P6 and Primavera Unifier Applications Using Schedule Sheets

Perform the steps below to link P6 to Primavera Unifier using schedule sheet integration. This link at the application level allows you to establish links at the project level. When the applications and projects are linked, P6 users can send data to Primavera Unifier schedule sheets.

To link P6 to Primavera Unifier using schedule sheet integration:

  1. Click Administration.
  2. On the Administration navigation bar, click Application Settings.
  3. On the Application Settings page, click the Integration and Allow Lists tab.
  4. On the Integration and Allow Lists tab:
    1. Enter a URL in the Primavera Unifier URL field of the Unifier section.
    2. Enter a Primavera Unifier integration user name in the Integration User Name field.
    3. Enter the Primavera Unifier password for the integration user name in the Password field.
    4. Click Save and Close.

Tip:

You need the Edit Application Settings privilege to edit the settings in the Application Settings page.

Related Topics

Working With Primavera Unifier

Linking P6 and Primavera Unifier Projects and Schedule Sheets.

Linking P6 and Primavera Unifier Applications Using Summary Sheets

Linking P6 and Primavera Unifier Projects and Summmary Sheets.

Linking P6 and Primavera Unifier Applications Using Activity Sheets

Linking P6 and Primavera Unifier Projects and Activity Sheets.

Filtering Data to be Sent to Primavera Unifier

Exchanging P6 data with Primavera Unifier



Legal Notices | Your Privacy Rights
Copyright © 1999, 2020

Last Published Friday, October 1, 2021