Update status to define percent complete and start and finish dates.
To update status:
- Click Projects.
- On the Projects navigation bar, click Activities.
- On the Activities page, select an activity and click the Status detail window.
- In the Status detail window:
- Select or clear the Started and Finished options.
- If you select an option, click Select Date and select a date from the calendar.
- Enter a percentage in the Activity % Complete field.
- Click Save.