You can share data with Oracle Primavera Cloud for Scope Management. You can send a scope management project and its work packages to P6. Then you can add activities to a work package in your P6 project so when you click Actions , select Exchange Data, and then select an appropriate action, your project and activity data will be sent to the Oracle Primavera Cloud scope management project.
Tips
- Before you can send data from P6 to Oracle Primavera Cloud for scope management, you must link the two applications. See Linking P6 and Oracle Primavera Cloud Applications.
- If the work package structure in Oracle Primavera Cloud changes, you can update your P6 project with the new structure by clicking Actions and selecting Exchange Data and and then select an action for updating data from Oracle Primavera Cloud.
- Do not modify the WBS structure, including WBS names and codes, once a project has been integrated with Oracle Primavera Cloud for scope management. Do not move activities between WBS nodes once a project has been integrated with Oracle Primavera Cloud for scope management.
- You need the Exchange Project Data with Oracle Primavera Cloud privilege to send data to Oracle Primavera Cloud.
- Scope data is not included if you copy and paste a project in P6 or P6 Professional connected to an EPPM database.
- If a project has been integrated with Oracle Primavera Cloud for scope management, when you check out a project in P6 Professional connected to an EPPM database, Scope and Work Package data is included with the checked out project.