Summary Tab of the View Calendar Dialog Box of the Activities Page, EPS Page, Assignments Page, or Resources Page

Overview

Use this tab to view a summary of all the settings for the calendar.

Screen Elements

Standard Work Week area:

Standard Work Week table

Enables you to see an overview of the work time periods configured for each day of the week in the calendar.

Time Periods area:

Hours per Time Period fields

The values that will be used as conversion factors when users choose to display time units and durations in units other than hours.

Base Calendar area:

Base Calendar field

The global calendar that is assigned to the calendar to determine nonwork days (for example, global holidays) and calendar exceptions.

For example, multinational corporations will have one or more global calendars per country to represent global holidays for each region. Exceptions are used when the standard work day is modified.

Exceptions area:

Date Range options

Determines the Start and Finish of the date range for which you want to view exceptions.

Exceptions table

Enables you to see a list of all the exceptions configured for the calendar within the selected date range.

Getting Here

From the Activities page:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. On the Activities page:
    1. Select an activity.
    2. Click Row Actions and select View Calendar.
  4. In the View Calendar dialog box, select Summary.

From the EPS page:

  1. Click Projects.
  2. On the Projects navigation bar, click EPS.
  3. On the EPS page:
    1. Select a project.
    2. Click Row Actions and select View Calendar.
  4. In the View Calendar dialog box, select Summary.

From the Assignments page:

  1. Click Resources.
  2. On the Resources navigation bar, click Assignments.
  3. On the Assignments page:
    1. Select an assignment.
    2. Click Row Actions and select View Calendar.
  4. In the View Calendar dialog box, select Summary.

From the Resources tab:

  1. Click Resources.
  2. On the Resources navigation bar, click Administration.
  3. On the Administration page, click the Resources tab.
  4. On the Resources tab:
    1. Select a resource.
    2. Click Row Actions and select View Calendar.
  5. In the View Calendar dialog box, select Summary.