Standard Work Week Tab of the View Calendar Dialog Box of the Activities Page, EPS Page, Assignments Page, or Resources Page

Overview

Use this tab to view the length of work hours in a day and the total number of hours worked in a particular day.

Screen Elements

Work area

The typical work week that can be modified by day and hour. After choosing a calendar to be added while on the calendar tab, the Standard Work Week tab will display the similar template by days and hours.

Day label

The name of each day. This label begins the week with Sunday, ends with Saturday.

Total Hours field

The total number of work hours for each day.

Calendar View area

Enables you to view a day, week, month, or year of the calendar to identify standard time, nonwork time and calendar exceptions.

Work Period display

Displays a box that represents each work period in a day. If you change the number of hours covered by the work period boxes for a day, P6 updates the Total Hours field.

Tips:

Getting Here

From the Activities page:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. On the Activities page:
    1. Select an activity.
    2. Click Row Actions and select View Calendar.
  4. In the View Calendar dialog box, select Standard Work Week.

From the EPS page:

  1. Click Projects.
  2. On the Projects navigation bar, click EPS.
  3. On the EPS page:
    1. Select a project.
    2. Click Row Actions and select View Calendar.
  4. In the View Calendar dialog box, select Standard Work Week.

From the Assignments page:

  1. Click Resources.
  2. On the Resources navigation bar, click Assignments.
  3. On the Assignments page:
    1. Select an assignment.
    2. Click Row Actions and select View Calendar.
  4. In the View Calendar dialog box, select Standard Work Week.

From the Resources tab:

  1. Click Resources.
  2. On the Resources navigation bar, click Administration.
  3. On the Administration page, click the Resources tab.
  4. On the Resources tab:
    1. Select a resource.
    2. Click Row Actions and select View Calendar.
  5. In the View Calendar dialog box, select Standard Work Week.