Project Header - Record 30

P6 EPPM Field

P6 EPPM Table Field

P6 EPPM Table

MPX Field

Project Name/WBS Name

wbs_name

PROJWBS

Project tab

n/a

defaults to empty string

n/a

Company

User Defined Field Title

User Defined Field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

Manager

The default project calendar is exported.

defaults to Standard

n/a

Calendar (Standard used if no entry)

Data Date

data_date

PROJECT

Start Date (either this field or the Finish Date field is calculated for an imported file, depending on the Schedule From setting)

Must Finish By

plan_end_date

PROJECT

Finish Date

(Calculated by P6 EPPM.)

n/a

defaults to 0

n/a

Schedule From
(0 = start,
1 = finish)

n/a

calculated by Microsoft Project (defaults to empty string)

n/a

Current Date

(Calculated by P6 EPPM.)

Notebook Description

wbs_memo

WBSMEMO

Comments

n/a

calculated by Microsoft Project (defaults to empty string)

n/a

Cost

(Calculated by P6 EPPM.)

n/a

calculated by Microsoft Project (defaults to empty string)

n/a

Baseline Cost

(Calculated by P6 EPPM.)

n/a

calculated by Microsoft Project (defaults to empty string)

n/a

Actual Cost

(Calculated by P6 EPPM.)

n/a

calculated by Microsoft Project (defaults to empty string)

n/a

Work

(Calculated by P6 EPPM.)

n/a

calculated by Microsoft Project (defaults to empty string)

n/a

Baseline Work

(Calculated by P6 EPPM.)

n/a

calculated by Microsoft Project (defaults to empty string)

n/a

Actual Work

(Calculated by P6 EPPM.)

n/a

calculated by Microsoft Project (defaults to empty string)

n/a

Work

(Calculated by P6 EPPM.)

n/a

calculated by Microsoft Project (defaults to empty string)

n/a

Duration

(Calculated by P6 EPPM.)

n/a

calculated by Microsoft Project (defaults to empty string)

n/a

Baseline Duration

(Calculated by P6 EPPM.)

n/a

calculated by Microsoft Project (defaults to empty string)

n/a

Actual Duration

(Calculated by P6 EPPM.)

n/a

calculated by Microsoft Project (defaults to empty string)

n/a

Percent Complete

(Calculated by P6 EPPM.)

n/a

calculated by Microsoft Project (defaults to empty string)

n/a

Baseline Start

(Calculated by P6 EPPM.)

n/a

calculated by Microsoft Project (defaults to empty string)

n/a

Baseline Finish

(Calculated by P6 EPPM.)

n/a

calculated by Microsoft Project (defaults to empty string)

n/a

Actual Start

(Calculated by P6 EPPM.)

n/a

calculated by Microsoft Project (defaults to empty string)

n/a

Actual Finish

(Calculated by P6 EPPM.)

n/a

calculated by Microsoft Project (defaults to empty string)

n/a

Start Variance

(Calculated by P6 EPPM.)

n/a

calculated by Microsoft Project (defaults to empty string)

n/a

Finish Variance

(Calculated by P6 EPPM.)

User Defined Field Title

User Defined Field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

Subject

User Defined Field Title

User Defined Field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

Keywords



Legal Notices | Your Privacy Rights
Copyright © 1999, 2020, Oracle and/or its affiliates. All rights reserved.

Last Published Tuesday, December 17, 2019