Task - Record 70

P6 EPPM Field

P6 EPPM Table Field

P6 EPPM Table

MPX Field

MPX Field ID

n/a

auto incremented value

n/a

ID

90

Unique ID

auto incremented value

TASK

Unique ID

98

Activity Name

task_name

TASK

Name

1

WBS Code

wbs_short_name

PROJWBS

WBS

2

n/a

calculated on export

n/a

Outline Level

3

Primary Constraint

See constraint sub-table.

cstr_type

TASK

Constraint Type

91

Primary Constraint Date

cstr_date

TASK

Constraint Date

68

Activity Leveling Priority

See activity leveling priority sub-table.

priority_type

TASK

Priority

95

Activity Type

task_type

TASK

Milestone = Yes
All other types = No

81

n/a

Yes = WBS levels
No = Activity tasks

n/a

Summary

120

n/a

Yes = WBS levels
No = Activity tasks

n/a

Rollup

84

At Completion Duration

total_drtn_hr_cnt

TASK

Duration

40

Planned Duration (P6 EPPM)

target_drtn_hr_cnt

TASK

Baseline Duration

41

Actual Duration

act_drtn_hr_cnt

TASK

Actual Duration

42

Remaining Duration

remain_drtn_hr_cnt

TASK

Remaining Duration

43

Duration Type

See duration type sub-table.

duration_type

TASK

Fixed

80

Predecessors

n/a

TASKPRED

Predecessors

70

Start

start_date

TASK

Start

50

Finish

end_date

TASK

Finish

51

Early Start

early_start_date

TASK

Early Start

(Calculated by P6 EPPM.)

52

Early Finish

early_end_date

TASK

Early Finish

(Calculated by P6 EPPM.)

53

Late Start

late_start_date

TASK

Late Start

(Calculated by P6 EPPM.)

54

Late Finish

late_end_date

TASK

Late Finish

(Calculated by P6 EPPM.)

55

n/a

defaults to 0

n/a

Delay

92

Free Float

free_float_hr_cnt

TASK

Free Slack

(Calculated by P6 EPPM.)

93

Total Float

total_float_hr_cnt

TASK

Total Slack

(Calculated by P6 EPPM.)

94

Duration % Complete

drtn_complete_pct

TASK

%Complete

(Calculated by P6 EPPM.)

44

Planned Start

target_start_date

TASK

Baseline Start

56

Planned Finish

target_end_date

TASK

Baseline Finish

57

Actual Start

act_start_date

TASK

Actual Start

58

Actual Finish

act_end_date

TASK

Actual Finish

59

At Completion Labor Units

total_work_qty

TASK

Work

20

Planned Labor Units (P6 EPPM)

Budgeted Labor Units or Planned Labor Units (P6 Professional)

target_work_qty

TASK

Baseline Work

21

Actual Labor Units

act_work_qty

TASK

Actual Work

22

Estimate At Completion Cost (actual cost + estimate to complete cost)

EAC

TASK

Cost

30

At Completion Expense Cost

total_expense_cost

TASK

Fixed Cost

35

Budget At Completion

(planned labor cost + planned nonlabor cost + planned expense cost in P6 EPPM)

(budgeted or planned labor cost + budgeted or planned nonlabor cost + budgeted or planned expense cost in P6 Professional)

BAC

TASK

Baseline Cost

31

Actual Cost (actual labor cost + actual nonlabor cost + actual expense cost)

ACWP

TASK

Actual Cost

32

Estimate to Complete (Remaining labor cost + remaining nonlabor cost + remaining expense cost)

ETC

TASK

Remaining Cost

33

User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

Text1-Text10

4-13

User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

Cost-Cost3

36-38

User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

Duration1-Duartion3

46-48

User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

Start1-Start5

60, 62, 64, 126, 128

User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

Finish1-Finish5

61, 63, 65, 127, 129

User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

Flag1-Flag10

110-119

User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

Number1-Number5

140-144

Constraint Sub-table

P6 EPPM Field

MPX Field

As late as possible

As late as possible

Finish on

Must finish on

Finish on or after

Finish no earlier than

Finish on or before

Finish no later than

Mandatory finish

Must finish on

Mandatory start

Must start on

Start on

Must start on

Start on or after

Start no earlier than

Start on or before

Start no later than

Activities without constraints

As soon as possible

Activity Leveling Priority Sub-table

P6 EPPM Field

MPX Field

5-Lowest (exports as 100)

Lowest (0-199)

4-Low (exports as 300)

Lower (300-399)

3-Normal (exports as 500)

Medium (500-599)

2-High (exports as 700)

Higher (700-799)

1-Top (exports as 900)

Highest (900-999)

Duration Type Sub-table

Fixed = Yes

Fixed = No

Fixed Duration and Units

Fixed Units

Fixed Duration and Units/Time

Fixed Units/Time