P6 EPPM Field | P6 EPPM Table Field | P6 EPPM Table | MPX Field |
---|---|---|---|
Resource ID Name | rsrc_id | TASKRSRC | ID |
Planned Units/Time (P6 EPPM) Budgeted Units/Time or Planned Units/Time (P6 Professional) | target_qty_per_hr | TASKRSRC | Units |
At Completion Units | total_qty | TASKRSRC | Work |
Planned Units (P6 EPPM) Budgeted Units or Planned Units (P6 Professional) See Note 2. | target_qty | TASKRSRC | Planned Work |
Actual Regular Units | act_reg_qty | TASKRSRC | Actual Work |
Actual Overtime Units | act_ot_qty | TASKRSRC | Overtime Work |
At Completion Cost | total_cost | TASKRSRC | Cost |
Planned Cost (P6 EPPM) Budgeted Cost or Planned Cost (P6 Professional) | target_cost | TASKRSRC | Planned Cost |
Actual Cost | act_cost | TASKRSRC | Actual Cost |
Start | start_date | TASKRSRC | Start (Calculated by P6 EPPM.) |
Finish | end_date | TASKRSRC | Finish (Calculated by P6 EPPM.) |
Lag | lag_drtn_hr_cnt | TASKRSRC | Assignment Delay |
n/a | defaults to empty string | n/a | Resource Unique ID |