Resource

Microsoft Project Field

P6 EPPM Table Field

P6 EPPM Table

P6 EPPM Field

Name

rsrc_name

RSRC

Resource Name

Resource Initials or
Resource Name

rsrc_short_name

RSRC

Resource ID

Max Units

max_qty_per_hr

RSRC

Max Units/Time

Standard Rate

cost_per_qty

RSRC

Price/Unit

Overtime Rate

cost_per_qty multiplied by ot_factor

RSRC

Price/Unit multiplied by Overtime Factor

Group

rsrc_name(of parent)

RSRC

Resource Name (of parent)

Email Address

email_addr

RSRC

Email Address

Type (work = labor, material = material)

rsrc_type

RSRC

Resource Type (labor, equipment, material)

Material Labor

unit_abbrev

UMEASURE

Unit of Measure

Cost Rate Tables

See cost rate sub-table.

start_date
cost_per_qty
cost_per_qty2
cost_per_qty3
cost_per_qty4
cost_per_qty5

RSRCRATE

Units & Prices

Notes

rsrc_notes

RSRC

Resource Notes

Text1-Text30

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

User Defined Field Title

Cost1-Cost10

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

User Defined Field Title

Date1-Date10

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

User Defined Field Title

Duration1-Duration1

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

User Defined Field Title

Number1-Number20

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

User Defined Field Title

Start1-Start10

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

User Defined Field Title

Finish1-Finish10

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

User Defined Field Title

Flag1-Flag20

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

User Defined Field Title

Baseline Cost1-
Baseline Cost10
(Microsoft Project 2002 and later)

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

User Defined Field Title

Baseline Work1-
Baseline Work10
(Microsoft Project 2002)

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

User Defined Field Title

Cost Rate Sub-table

Microsoft Project Field

P6 EPPM Field

Effective Date

Effective Date

Standard Rate A

Price/Unit 1

Standard Rate B

Price/Unit 2

Standard Rate C

Price/Unit 3

Standard Rate D

Price/Unit 4

Standard Rate E

Price/Unit 5