Task

Microsoft Project Field

P6 EPPM Table Field

P6 EPPM Table

P6 EPPM Field

ID

auto-increment or Microsoft Project ID

TASK

Activity ID

Name

task_name

TASK

Activity Name

WBS

wbs_short_name

PROJWBS

WBS Code

Outline Level

builds the WBS structure

n/a

n/a

Constraint Type

See constraint type sub-table.

cstr_type

TASK

Primary Constraint

Constraint Date

cstr_date

TASK

Primary Constraint Date

Priority

See activity leveling priority sub-table.

priority_type

TASK

Activity Leveling Priority

Task or Milestone

See activity type sub-table.

task_type

TASK

Activity Type

Duration

total_drtn_hr_cnt

TASK

At Completion Duration

Baseline Duration

target_drtn_hr_cnt

TASK

Planned Duration (P6 EPPM)

Original Duration or Planned Duration (P6 Professional)

Actual Duration

act_drtn_hr_cnt

TASK

Actual Duration

Remaining Duration

remain_drtn_hr_cnt

TASK

Remaining Duration

Task Type

See duration type sub-table.

duration_type

TASK

Duration Type

Predecessors

n/a

TASKPRED

Predecessors

Start

start_date

TASK

Start

Finish

end_date

TASK

Finish

Early Start

early_start_date

TASK

Early Start

Early Finish

early_end_date

TASK

Early Finsih

Late Start

late_start_date

TASK

Late Start

Late Finish

late_end_date

TASK

Late Finish

Baseline Start

target_start_date

TASK

Planned Start

Baseline Finish

target_end_date

TASK

Planned Finish

Actual Start

act_start_date

TASK

Actual Start

Actual Finish

act_end_date

TASK

Actual Finish

Work

total_work_qty

TASK

At Completion Labor Units

Baseline Work

target_work_qty

TASK

Planned Labor Units (P6 EPPM)

Budgeted Labor Units or Planned Labor Units (P6 Professional)

Actual Work

act_work_qty

TASK

Actual Labor Units

Cost

EAC

TASK

Estimate At Completion Cost
(actual cost + estimate to complete cost)

Fixed Cost

total_expense_cost

TASK

At Completion Expense Cost

Baseline Cost

BAC

TASK

Budget At Completion

(planned labor cost + planned nonlabor cost + planned expense cost in P6 EPPM)

(budgeted or planned labor cost + budgeted or planned nonlabor cost + budgeted or planned expense cost in P6 Professional)

Actual Cost

ACWP

TASK

Actual Cost (actual labor, nonlabor, and expense cost)

Fixed Cost Accrual

See accrual type sub-table

cost_load_type

PROJCOST

Accrual Type

Task Calendar

clndr_id (foreign key)

TASK

Activity Calendars

Deadline

(Microsoft Project 2000 and later)

expect_end_date

TASK

Expected Finish

Physical % Complete
(Microsoft Project 2002 and later)

phys_complete_pct

TASK

Physical % Complete

Remaining Cost

ETC

TASK

Estimate To Complete
(Remaining labor, nonlabor, and expense cost)

Notes

task_memo

TASKMEMO

Notebook Description

Text1-Text30

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

User Defined Field Title

Cost1-Cost10

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

User Defined Field Title

Duration1-Duration10

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

User Defined Field Title

Start1-Start10

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

User Defined Field Title

Finish1-Finish10

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

User Defined Field Title

Flag1-Flag20

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

User Defined Field Title

Number1-Number20

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

User Defined Field Title

Date1-Date10

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

User Defined Field Title

Baseline Cost1-Baseline Cost10

(Microsoft Project 2002 and later)

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

User Defined Field Title

Baseline Duration 1-Baseline Duration10

(Microsoft Project 2002 and later)

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

User Defined Field Title

Baseline Work1-Baseilne Work10

(Microsoft Project 2002 and later)

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

User Defined Field Title

Activity ID

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

User Defined Field Title

Constraint Sub-table

Microsoft Project Field

P6 EPPM Field

Must start on

Mandatory Start

Start no later than

Start on or before

Start no earlier than

Start on or after

Must finish on

Mandatory Finish

Finish no earlier than

Finish on or after

Finish no later than

Finish on or before

As late as possible

As late as possible

As soon as possible

Activities without constraints

Activity Leveling Priority Sub-table

Microsoft Project Field

P6 EPPM Field

Highest

Top

Higher

High

Medium

Medium

Lower

Low

Lowest

Lowest

Activity Type Sub-table

Microsoft Project Field

P6 EPPM Field

Task - Scheduling Ignores Resource Calendars is selected

(Microsoft Project 2000 and later)

Task Dependent

Task - Scheduling Ignores Resource Calendars is not selected

(Microsoft Project 2000 and later)

Resource Dependent

Milestone - Mark Task as Milestone is selected

Task imported as a Start Milestone

Duration Type Sub-table

Microsoft Project Field

P6 EPPM Field

Fixed Duration (Effort Driven No)

Fixed Duration and Units/Time

Fixed Units (Effort Driven Yes)

Fixed Units/Time

Fixed Work (Effort Driven No)

Fixed Units

Fixed Duration (Effort Driven Yes)

Fixed Duration and Units

Fixed Units (Effort Driven No)

Fixed Units/Time

Accrual Type Sub-table

Microsoft Project Field

P6 EPPM Field

Start

Start of Activity

Prorated

Uniform over Activity

End

Finish of Activity