Task

P6 EPPM Field

P6 EPPM Table Field

P6 EPPM Table

Microsoft Project Field

n/a

auto-generated by Microsoft Project

n/a

ID

Activity Name

task_name

TASK

Name

WBS Code

wbs_short_name

PROJWBS

WBS

n/a

calculated on export

n/a

Outline Level

Primary Constraint

See constraint sub-table.

cstr_type

TASK

Constraint Type

Primary Constraint Date

cstr_date

TASK

Constraint Date

Activity Leveling Priority

See activity leveling priority sub-table.

priority_type

TASK

Priority

Activity Type

See activity type sub-table.

task_type

TASK

Task or Milestone

At Completion Duration

total_drtn_hr_cnt

TASK

Duration

Planned Duration (P6 EPPM)

Original Duration or Planned Duration (P6 Professional)

target_drtn_hr_cnt

TASK

Baseline Duration

Actual Duration

act_drtn_hr_cnt

TASK

Actual Duration

Remaining Duration

remain_drtn_hr_cnt

TASK

Remaining Duration

Duration Type

See duration type sub-table.

duration_type

TASK

Task Type

Predecessors

n/a

TASKPRED

Predecessors

Start

start_date

TASK

Start

Finish

end_date

TASK

Finish

Early Start

early_start_date

TASK

Early Start

Early Finish

early_end_date

TASK

Early Finish

Late Start

late_start_date

TASK

Late Start

Late Finish

late_end_date

TASK

Late Finish

Planned Start

target_start_date

TASK

Baseline Start

Planned Finish

target_end_date

TASK

Baseline Finish

Actual Start

act_start_date

TASK

Actual Start

Actual Finish

act_end_date

TASK

Actual Finish

At Completion Labor Units

total_work_qty

TASK

Work

Planned Labor Units (P6 EPPM)

Budgeted Labor Units or Planned Labor Units (P6 Professional)

target_work_qty

TASK

Baseline Work

Actual Labor Units

act_work_qty

TASK

Actual Work

Estimate At Completion Cost

(actual cost + estimate to complete cost)

EAC

TASK

Cost

At Completion Expense Cost

total_expense_cost

TASK

Fixed Cost

Budget At Completion

(planned labor cost + planned nonlabor cost + planned expense cost in P6 EPPM)

(budgeted or planned labor cost + budgeted or planned nonlabor cost + budgeted or planned expense cost in P6 Professional)

BAC

TASK

Baseline Cost

Accrual Type

See accrual type sub-table.

cost_load_type

PROJCOST

Fixed Cost Accrual

Activity Calendars

clndr_id (foreign key)

TASK

Task Calendar

Expected Finish

expect_end_date

TASK

Deadline

(Microsoft Project 2000 and later)

Physical % Complete

phys_complete_pct

TASK

Physical % Complete

(Microsoft Project 2002 and later)

Estimate To Complete (Remaining labor, nonlabor, and expense cost)

ETC

TASK

Remaining Cost

Notebook Description

task_memo

TASKMEMO

Notes

User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

Text1-Text30

User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

Cost1–Cost10

User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

Duration1-Duration10

User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

Start1-Start10

User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

Finish1-Finish10

User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

Flag1-Flag20

User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

Number1-Number20

User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

Date1 – Date10

User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

Baseline Cost1 – Baseline Cost10

(Microsoft Project 2002 and later)

User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

Baseline Duration1 – Baseline Duration10

(Microsoft Project 2002 and later)

User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

Baseline Work1 – Baseline Work10

(Microsoft Project 2002 and later)

User Defined Field Title

User defined field

(The Activity ID Setting applies when you are updating an existing imported project.)

UDFVALUE

Activity ID

Constraint Sub-table

P6 EPPM Field

Microsoft Project Field

Start on

Must start on

Start on or before

Start no later than

Start on or after

Start no earlier than

Mandatory Start

Must start on

Finish on

Must finish on

Finish on or after

Finish no earlier than

Finish on or before

Finish no later than

Mandatory Finish

Must finish on

As late as possible

As late as possible

Activities without constraints

As soon as possible

Activity Leveling Priority sub-table

P6 EPPM Field

Microsoft Project Field

Top

Highest

High

Higher

Medium

Medium

Low

Lower

Lowest

Lowest

Activity Type Sub-table

P6 EPPM Field

Microsoft Project Field

Task Dependent

Task - Scheduling Ignores Resource Calendars is selected

(Microsoft Project 2000 and later)

Resource Dependent

Task - Scheduling Ignores Resource Calendars is not selected

(Microsoft Project 2000 or later)

Start Milestone

Milestone - Mark Task as Milestone is selected

Finish Milestone

Milestone - Mark Task as Milestone is selected

Level of Effort

Task - Scheduling Ignores Resource Calendars is not selected

(Microsoft Project 2000 and later)

Duration Type Sub-table

P6 EPPM Field

Microsoft Project Field

Fixed Duration and Units/Time

Fixed Duration (Effort Driven No)

Fixed Units/Time

Fixed Units (Effort Driven Yes)

Fixed Units

Fixed Work (Effort Driven No)

Fixed Duration and Units

Fixed Duration (Effort Driven Yes)

Fixed Units/Time

Fixed Units (Effort Driven No)

Accrual Type Sub-table

P6 EPPM Field

Microsoft Project Field

Start of Activity

Start

Uniform over Activity

Prorated

Finish of Activity

End