Microsoft Project Field | P6 EPPM Table Field | P6 EPPM Table | P6 EPPM Field |
---|---|---|---|
Default Task Type See default type sub-table. | def_duration_type | PROJECT | Default Duration |
Default Task Type Sub-table
Microsoft Project Field | P6 EPPM Field |
---|---|
Fixed Duration | Fixed Duration and Units/Time |
Fixed Units | Fixed Units/Time |
Fixed Work | Fixed Units |