Microsoft Project Field | P6 EPPM Table Field | P6 EPPM Table | P6 EPPM Field |
---|---|---|---|
Fiscal year starts in | fy_start_month_num | PROJECT | Fiscal Year Begins |
Hours Per Day | day_hr_cnt | CALENDAR | Work Hours Per Day |
Hours Per Week | week_hr_cnt | CALENDAR | Work Hours Per Week |
Notes:
- Calendars in P6 EPPM additionally have settings for Work Hours Per Month and Work Hours Per Year. Microsoft Project does not have equivalent fields. To calculate Work Hours Per Month, P6 EPPM applies the following formula: Days Per Month (as defined in Microsoft Project) multiplied by Hours Per Day. Using the value derived from this calculation, P6 EPPM applies the following formula to calculate Work Hours per Year: Work Hours per Month multiplied by 12.
- Calendar hours per timeperiod settings in Microsoft Project are only imported if the Use assigned calendar to specify the number of work hours for each time period option is selected on the time periods page of application settings in P6 EPPM or the time periods page of admin preferences in P6 Professional.
- Working time calendars in Microsoft Project are imported as project-level calendars. Resource working time calendars in Microsoft Project are imported as resource-level calendars.