Resource Assignment

P6 EPPM Field

UN/CEFACT Field

RA_+ActivityObjectId_+ResourceObjectId+ACP/BCP/EST+_DC/HR/UN or

RA + ActivityObjectId + RoleObjectId+ ACP/BCP/EST+_DC/HR/UN

ID

 ACP/BCP/EST

CostManagementCode

ActualCost, BudgetedCost, RemainigCost

ResourceAmount

Value = ‘FALSE’

DurationBasedIndicator

Actual Units, Budgeted Units, Remaining Units

HourResourceQuantity

Actual Units, Budgeted Units, Remaining Units for Material Resource

MaterialResourceQuantity

Planned lag

AllocatedProjectPeriod.ProjectPeriod.DurationMeasure

ResourceObjectId/RoleObjectId

AllocatedProjectResource.ID

Resource Name

AllocatedProjectResource.Name

Value = ‘DC’/’HR’/’UN’

AllocatedProjectResourc.PlanMeasureTypeCode

Resource Type

AllocatedProjectResourc.CostCategoryCode

Actual Duration,
Planned Duration, Remaining Duration

AllocatedProjectResourc.AvailabilityProjectPeriod.DurationMeasure

Actual Start Date,
Planned Start Date, Remaining Start Date

AllocatedProjectResourc.AvailabilityProjectPeriod.StartDateTime

Actual Finish Date,
Planned Finish Date, Remaining Finish Date

AllocatedProjectResourc.AvailabilityProjectPeriod.EndDateTime

CalendarObjectId

ScheduleProjectScheduleCalendar.ProjectScheduleCalendar.ID

ResourceCurveObjectId

AllocationResourceDistribution.ResourceDistributionProfile.ID

Resource Curve Name

AllocationResourceDistribution.ResourceDistributionProfile.Name

Calculated (21 points)

AllocationResourceDistribution.ResourceDistributionProfile.SpecifiedResourceDistributionProfilePoint.ResourceDistributionProfilePoint.Name

Percentage value for each of the 21 points

AllocationResourceDistribution.ResourceDistributionProfile.SpecifiedResourceDistributionProfilePoint.ResourceDistributionProfilePoint.AllocationPercent