- Choose Projects, Activities.
- Select the activity whose CBS assignment you want to define or change.
- In the Activity Table, double-click in the CBS column, then click .
- Select the CBS code to which you want to assign the selected activity. CBS codes are created in Primavera Unifier for the linked project's cost sheet.
- Click the Select button.