A restriction you impose on an activity or work unit with positive float that allows it to start as late as possible without delaying its successors. This constraint sets the early dates as late as possible without affecting successor activities.
A restriction you impose on an activity or work unit with positive float that allows it to start as late as possible without delaying its successors. This constraint sets the early dates as late as possible without affecting successor activities.