Use the Assign Baselines dialog to assign project, primary, secondary, and tertiary baselines to a project.
Project: Lists all open projects. Select the project to which you want to assign baselines.
Project Baseline: Lists the available baselines for the selected project. Select the baseline to use as the project baseline. If a baseline does not exist, the current project is the default value.
User Baselines
Primary: Select the primary baseline from the list of available baselines. If a baseline does not exist, the current project is the default value.
Secondary: Select the second baseline from the list of available baselines. A second baseline is not required.
Tertiary: Select the tertiary baseline from the list of available baselines. A tertiary baseline is not required.
OK: Click to assign the selected baselines to the selected project.
Cancel: Closes the dialog without saving your changes.