- Choose Enterprise, Projects, then select the EPS node or project you want to copy.
- Choose Edit, Copy.
- Click the location in the EPS where you want to paste the new EPS node/project.
- Choose Edit, Paste.
- Mark the checkboxes beside any optional information you want to include in the copied EPS node or project in the Copy Project Options, Copy WBS Options, and Copy Activity Options dialog boxes.
Notes:
- When connected to a P6 EPPM database: When you copy an EPS node, any template projects in that EPS are copied even though you cannot see them in P6 Professional.
- When connected to a P6 EPPM database: P6 Professional uses a job service to copy projects and EPS nodes. This means that you can carry on working while the project or EPS is copied in the background. To see the progress of the job, choose Tools, Job Status.
- The administrator should not assign any of the following privileges to users who should not have access to view cost information while copying and pasting project/EPS or assigning WBS and Fill Down on the WBS column in the Activities view: View Project Costs/Financials, Edit WBS Costs/Financials, and Edit EPS Costs/Financials.
- You must group the projects (to copy) by EPS in order to copy Summary Data.
Tip
When you select an EPS node to copy, all of the selected EPS node’s subordinate EPS nodes/projects are also copied, even if you do not select them.