Use the Copy Project Options dialog box to specify which optional project information you want to copy when you create a copy of an existing project.
Risks: When connected to a P6 EPPM database, mark this checkbox to copy P6 risk information to the new project. When connected to a P6 Professional database, mark this checkbox to copy risk information to the new project.
Issues and Thresholds: Mark this checkbox to copy issue and threshold information to the new project.
Reports: Mark this checkbox to copy reports to the new project.
Documents: Mark this checkbox to copy documents to the new project.
Funding Sources: Mark this checkbox to copy funding sources to the new project.
Baselines: Mark this checkbox to copy baselines to the new project. Note: if the project you are copying does not contain any baselines, this checkbox will be disabled.
Summary Data: Mark this checkbox to copy summary data to the new project.
Enable Publication for copied projects: Mark this checkbox to enable the publication option for the new project.
Do not show this dialog again: Mark to indicate that you do not want this dialog box to appear next time you create a copy of a project.