- Select the activities you want to cut and paste.
- Choose Edit, Cut.
- Select the WBS band where you want to insert the cut activities, then choose Edit, Paste.
Note:
When connected to a P6 EPPM database: When you cut and paste activities within the same project, any associated risks from P6 are also moved; risks from P6 are not moved when you cut and paste activities to a different project.
When connected to a P6 Professional database: When you cut and paste activities within the same project, any associated risks are also moved; risks are not moved when you cut and paste activities to a different project.