- Choose Project, Activities.
- Select the activity whose unit values you want to record.
- Display Activity Details, then click the Resources tab.
- To enter the budgeted or planned units for the activity, type the value in the budgeted or planned Units column.
To enter the actual units for the activity, type the value in the Actual Units column. You can only enter actual units for activities that are in progress or completed.
To enter the remaining units for the activity, type the value in the Remaining Units column. You can only enter remaining units for activities that are in progress.
Note
- A time period does not display if the Show Unit Label checkbox is not marked in the User Preferences, Time Units tab.
Tips
- P6 Professional automatically recalculates the time value and period you enter according to the standard time period defined by your system administrator.
- To view the available time period abbreviations, choose Admin, Admin Preferences, then click the Time Periods tab when P6 Professional is connected to a P6 Professional database and choose the Application Settings in P6 when connected to a P6 EPPM database.
Synchronizing activity duration, units, and resource units/time