A Finish Date Variance threshold value is a specified number of days. An issue is generated if the difference between the activity's baseline and current finish dates (calculated as BL Finish - Finish Date) falls beyond the threshold values. If no baseline is defined, the current project is used as the primary baseline.
A negative value for Finish Date Variance indicates that the current finish date is later than the primary baseline finish date.