Modify check in update options for an XML file
- Open the projects you want to check in.
- Choose File, Check In, then select the project you want to check in.
- In the Update Project Options dialog box, select the layout you want to modify and click Modify.
- In the Modify Import Configuration dialog box, select the data you want to modify.
- Select the action to perform during the check-in process.
- Mark the Delete checkbox to remove unreferenced data, data in the project you are updating but not included in the check-out file, from the project.
- Click OK.
Note
- The Delete field applies only to relationships to external projects, thresholds, activities, activity relationships, and activity resource assignments. Global data types are not affected by this setting.