- Choose Project, Activities.
- Select the activity from which you want to remove a resource.
- Display Activity Details, then click the Resources tab.
- Select the resource you want to remove, then click Remove.
- Click Yes.
Notes
- When you remove all resources from the activity, you are prompted to choose whether or not to reset the labor/ nonlabor units to zero on the activity. Click Yes to set the Budgeted or Planned and Remaining Labor/ Nonlabor Units to zero.
- If you manually plan future period resource allocation, when you remove a resource assignment that has manual future period values from an activity, all manual future period values are deleted. If you want to preserve the manual values, you should replace the resource assigned to the activity.
Assign resources to activities
Display window details
Manual future period buckets
Replace resources assigned to activities