- Choose Enterprise, Projects and display Project Details.
- Click the Defaults tab.
- In the Defaults for New Activities section, select a default calendar.
Tip
- Click the Options bar in the Select Default Project Calendar dialog box to display global or project calendars.
Note
- The default calendar is only used for new activities. Changing this setting does not affect existing activities.