Show or hide overtime information in the Resource Usage Profile
- In the Activities window, choose View, Show on Bottom, Resource Usage Profile.
You can also click the Layout Options bar, then choose Show on Bottom, Resource Usage Profile.
- In the right pane of the bottom layout window, click the Display Options bar and make sure Show All Projects is not selected. A check next to Show All Projects indicates that it is selected.
- Click the Display Options bar again and choose Resource Usage Profile Options.
You can also right-click in the profile and choose Resource Usage Profile Options.
- Click the Data tab.
- Mark or clear the Show Overtime checkbox.
Note
- The Show Overtime checkbox displays only when you view resources for a specific project. It is not available when viewing projects across the enterprise.