You can view resource available units only in the total allocation resource profile, not when displaying the Resource Profile for selected projects.
- Display the profile in the Bottom Layout window, click the Display Options bar, and choose Bottom Layout Options, Profile Settings.
You can also click in the Bottom Layout window toolbar. - Click the Data tab.
- In the Display area, choose Units.
- In the Additional Data Options area, mark or clear the Show Available Units checkbox.
Notes
- Although the Show Available Units checkbox is available only when you are viewing resource allocation for all projects across the enterprise, you can edit your user preferences to show resource availability only for open projects. In the Resource Usage/Role Profile Options dialog box, click Preferences, then click the Resource Analysis tab. In the All Projects section, choose Opened Projects Only.
- Bars and cumulative curves with negative values do not display in the profile. You can view the negative values in the profile details. Double-click on the profile to view the profile details.