Modify calendar days to account for work or nonwork days or hours that are different than the standard hours defined on the Standard Work Week tab.
To modify work or nonwork calendar days:
- Click Administration.
- On the Administration navigation bar, click Enterprise Data.
- On the Enterprise Data page, expand Global and click Global Calendars.
- On the Global Calendars page:
- Click on the calendar you want to modify.
- Click the Calendar tab.
- On the Calendar tab, click the Date list for a date and select Set to Standard or Nonwork.
- Click Save.