Migrate projects to shells

Before you begin: See the considerations and mapping discussed in Creating a Business Process record from a template.

Step 1: Export the migration template. Export the CSV template. This template will vary depending on the data elements included in the configuration of a particular shell type. This template contains the fields and format that the system needs to migrate the standard projects to CBS shells. See Export the migration template.

Step 2: Modify the exported CSV template. Be sure that you have the correct project information ready to enter into the template. After you convert a standard project into a CBS shell, you cannot reverse the conversion. See Modify the exported csv template.

Step 3: Initiate migration. Import the completed CSV file. See Initiate migration of standard projects to CBS shells

Step 4: View migration history. See View migration history.

Step 5: Test for shell creation. See Test for CBS shell creation.

You export the template, then modify it and import it. You will export the template from a selected CBS shell, and then import the modified template back into the same CBS shell to complete the migration.

Related Topics

Export the migration template

Modify the exported csv template

Initiate migration of standard projects to CBS shells

View migration history

Test for CBS shell creation