Update Linked Schedule Sheets from Project or Shell Templates

  1. Go to the Company Workspace tab and switch to Admin mode.
  2. Click Templates in the left Navigator.
    • For a project template, in the left Navigator, click Templates > Projects (Standard) > [project] > [project template] > Schedule Manager > Schedule Sheets.
    • For a shell template, in the left Navigator, click Templates > Shells > [shell type] > [shell template] > Schedule Manager > Schedule Sheets.
  3. On the Schedule Sheets log, select the Schedule Sheet template that should update the activities on the linked schedule sheets.
  4. Click Update > Linked Schedule Sheets.

Unifier will update the activities and columns on all the schedule sheets that are linked to the template. It will not, however, push changes to activity dates.

Impact on Scope Management

Scope Management setups that are updated through the use of linked schedule sheets allow updates to any activities that are not yet initiated. This includes business process name, responsible users, duration flag, completion conditions.