uuu_duration_baseline[1...10]

Data Definition: Decimal Amount

Form Label (Field Label): Baseline Duration

# of Characters: Not applicable

Where to use it:

Use this element for: Displaying the baseline duration of a project phase on a schedule sheet.

This element produces an automatic formula of: duration = finish - start.

This is one element of a set that includes uuu_start_baseline[1...10] and uuu_finish_baseline[1...10]. You must include all 3 of these elements on the form for the baseline function to work correctly.