The Mapped Projects tab lists the P6 projects drawn from the Integration tab of shell details into the Activity Sheet.
The Mapped Projects tab toolbar options are:
The toolbar options are:
- Assign Rate Sheet
See below for details.
- Recost
See below for details.
- Refresh
- Find on Page
Use the toolbar options to assign a shell-level rate sheet to selected projects, recost resource loaded or cost loaded projects, refresh page, and find an item displayed on the page respectively.
The Mapped Projects tab columns are:
- Project ID
- Project Name
- Project Type: The values are Current or Baseline
- Project Start Date
- Data Date: The date a project is updated in P6
- Schedule Type: The values are Duration, Resource, or Cost
- ETC Technique: The formula used to calculate the Estimate to Complete. For example: PF = 1/CPI; PF = 1; (1/CPI)*(BAC - EV); 0.75 * (BAC – EV)
- Rate Sheet (Planning): The Master Rate Sheet or a shell-level rate sheet used to calculate the costs.
- Rate Sheet (Actuals): The Master Rate Sheet or a shell-level rate sheet used to calculate the costs.