About Unifier and P6 Integration

You can integrate multiple P6 projects into one Unifier project.

Prior to the Unifier 20.7 release:

When you performed Get Data from the Activity Sheets log, if the P6 Project ID was not defined in the Shell Attribute form (General tab and Integration tab), then Unifier would use the first import synchronization: Select Synchronization to Exchange Activity Data.

When you performed Get Data from the Activity Sheets log, if the P6 Project ID was defined in the Shell Attribute form (General tab and Integration tab), then Unifier would the second import synchronization: Select Synchronization to Exchange Activity and Assignment Data.

Starting with the Unifier 20.7 release:

When you performed Get Data from the Activity Sheets log, whether the P6 Project ID is defined, or the P6 Project ID is not defined, in the Shell Attribute form (General tab and Integration tab), Unifier uses a single import synchronization: Select Synchronization to Exchange Activity Data.

The drop-down field (Select Synchronization to Exchange Activity Data) displays all of the import synchronizations defined in Gateway for Unifier deployment, including the import synchronizations to get activity and assignment data which is used for EVM.

The system refers to the drop-down field (Select Synchronization to Exchange Activity Data) for the import synchronization selected in all of the following cases:

  1. P6 Project ID is added in the Integration tab
  2. P6 Project ID is added in the Shell Attribute form
  3. When the project number in the Shell Attribute form matches with the P6 project number.

Update of CBS Codes from P6

You can get the latest CBS Codes updates assigned to activities from P6 into the activity sheet, using gateway integration.

The Get Data synchronization that creates the activity sheet populates the following data:

You can use P6 to capture duration as well as resource assignments (resource units, resource CBS assignment, resource units spread, actual resources consumed till date, and so forth). The Activity Sheet, in this case, can receive all of the resource units, CBS assignments, and calculate costs using P6 data and rates.

Note: The export of CBS Cost codes from Unifier remain as is.

You can receive the latest updated CBS assignments to Activities and Resources and Role assignments when P6 data is pulled into the Activity Sheet. After the latest Get Data, you will be able to see that the CBS assignments updated in the Activity Sheet and re-costing sums the costs, by the latest CBS assignments. This applies to the existing Activities and Resources and Role in the Activity Sheet.

Note: All of the cost calculations will be updated based on the CBS assignment updates. In addition, any new earned value analysis (EVA) created will show the EVM data according to updated CBS Codes.

The following scenarios explain how to get the latest CBS codes updates assigned to activities from P6 into the activity sheet using gateway integration: