Creating Project Closeout Record

Create a Project Closeout record in the Tasks log to log your project closeout information.

On the Project Closeout form, specify a title for the record. Select the items that have been completed and specify the date of completion. Click Finish Editing to save the record.

Note: You must enter a value in all required fields (*) before you can save the form.

  1. Go to your project and ensure that you are in User Mode.
  2. Expand the Project Closeout node.
  3. Click Project Closeout.
  4. From the BP log page, click Create.The Create New Project Closeout Record form opens. (Required) In the Title field, enter a title.
  5. (Required) From the Status list, select an option.
  6. Select the Architectural Punchlist Signoff check box
  7. Click the Date/Time icon, select a date to specify the signoff date, and click OK.
  8. Select the Civil Punchlist Signoff check box
  9. Click the Date/Time icon, select a date to specify the signoff date, and click OK.
  10. Continue on with checking the completed items and specifying the date for each completed item.
  11. When finished, click Finish Editing, and click OK to complete creating a Project Closeout record.