Creating an Estimates Record

To create a new Estimates record

  1. Go to your project. Ensure that you are in the User mode.
  2. Expand the Financial Transactions.
  3. Select Estimates.
  4. From the BP log page, click Create.In the Create New Estimates form:
    1. Complete, at minimum, the required fields according to the Upper form table below. You can save the form as a draft at any time. Unifier stores the draft in the Drafts folder.
    2. In the Line Items section click Add or Grid. The Line Items form opens.
    3. Complete the Line Items form according to the Line Items table below. You must complete all required fields on each line that you entered before you can save the Line Items form.
    4. Click OK (if using the Line Item form), or Save (if using the grid) to save the form. The Line Items form closes.
    5. If you are using the grid and do not click Save before closing it, you will lose your line item changes.

Upper Form

In this field

Do this

General block

Record Number

This is a read-only field that Unifier populates the first time you save the form.

Title

This is a required field - Enter a name for the record.

Project Number

This is a read-only field that is auto-populated from the project's shell.

Project Name

This is a read-only field that is auto-populated from the project's shell.

Creator

This is a read-only field that identifies the person that created the record. The field appears as a link to the creator's contact information.

Creation Date

This is a read-only field that Unifier populates when you initially saved the form and it became a record.

Record Last Update Date

This is a read-only field that Unifier populates when you save a record.

Status

This is a read-only field that changes depending upon the records editable state.

Contract Reference

Select the contract from those listed in the Contracts log.

Potential Changes Reference

Select a Potential Changes record to associate with this estimate.

Estimate Type

Select a value from the Estimate Type drop-down menu.

Amount

This is an auto-calculated field that shows the total amount of the line items.

Description

In this field

Do this

Description

Enter a description for the record

P6 Activity Details

In this field

Do this

P6 Activity

Select the P6 activity you want associated with this estimate.

P6 Planned Start

This value comes from the P6 activity.

P6 Planned Cost

This value comes from the P6 activity.

P6 Planned Finish

This value comes from the P6 activity.