Unifier supports out of the box (OOTB) mapping for integration between P6 and Unifier, using Schedule Sheets.
This OOTB mapping is available as part of Project Control installation as a shell template (T-002). You must create a new shell by copying shell template (T-002) in order to integrate P6 and Unifier using Schedule Sheets.
To view the data mapping fields in Unifier:
- Go to Company Workspace > Admin mode > Templates > Shells > Projects.
- Open the T-002 (Project #) Owner Project Template(Project Name).
- From the left-hand navigator, click Schedule Manager > Schedule Sheets.
- In the Schedule Sheets log, open Project Schedule Sheet.
- From the menu bar, click File > Data Mappings.
- Click P6 (to select) > Modify > Activity tab.
The column name and XML elements are listed as shown below. You can use the XML elements for integration with P6.
Column | XML Element |
---|---|
Activity Name | Name |
Activity Percent | PercentComplete |
Actual Finish Date | ActualFinishDate |
Actual Start Date | ActualStartDate |
Duration | PlannedDuration |
Early Start date | EarlyStartDate |
Early finish date | EarlyFinishDate |
Finish date | PlannedFinishDate |
Late Start date | LateStartDate |
Late finish date | LateFinishDate |
P6 Activity Number | Id |
P6 CBS | CBSCode |
Start date | PlannedStartDate |