Project level

The sheet displays utilization of resources as a percentage at the project level and is shown for each resource-role combination.

Utilization% = (Total Assigned Hours / Hard-booked Hours) *100

This sheet cannot be opened unless the Schedule Manager is loaded or a master schedule sheet is created.

To view the project-level utilization summary sheet

In the project-level Resource Sheets log, select Utilization Summary Sheet and click Open. You can view this sheet by hours only.